October 22, 2018 Leave a Comment

Making Our Fusion Reactor Better, day 169 of 320: welding continues with two crews working simultaneously. Whatever you do, do not watch that arc ⚡️

https://davidpace.com/1718-2/

Filed Under: Microblog

October 19, 2018 Leave a Comment

Making Our Fusion Reactor Better, day 166 of 320: welding of the high strength steel begins! The frame rail (blue/silver with arc) is laid on top of the concrete base, but extends beyond it. Separate beams are visible beneath the frame rail, and now all must be welded together.

https://davidpace.com/1715-2/

Filed Under: Microblog

October 18, 2018 Leave a Comment

Making Our Fusion Reactor Better, day 165 of 320: Is Microsoft Project the most complicated piece of software ever created?

https://davidpace.com/1712-2/

Filed Under: Microblog

October 17, 2018 Leave a Comment

Making Our Fusion Reactor Better, day 164 of 320: parking lot demolition began yesterday. This particular area of parking will be reserved for handicapped access, which means that it needs to made level… and it was far from level to begin with ?

https://davidpace.com/1709-2/

Filed Under: Microblog

October 16, 2018 2 Comments

Two toddlers = compost pile that is 80% banana peels ?

https://davidpace.com/1707-2/

Filed Under: Microblog

October 15, 2018 Leave a Comment

Making Our Fusion Reactor Better, day 162 of 320: we have passed the halfway mark! Halfway through the calendar, at least, not halfway through the construction and task list ?

https://davidpace.com/1705-2/

Filed Under: Microblog

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 17
  • Page 18
  • Page 19
  • Page 20
  • Page 21
  • Interim pages omitted …
  • Page 57
  • Go to Next Page »

Copyright © 2025 · David Pace